The works involved constructing the reinforced concrete foundations required to support the modular building installation, together with the delivery of extensive drainage and below ground service infrastructure.
McCoysi nstalled new drainage networks and successfully connected these systems into existing prison infrastructure while also constructing a hardstanding slab adjoining the plant room area. The completed works provided the fully serviced platform necessary for the installation of the new modular holding and accommodation units.
Operating within a live prison environment presented a number of logistical and security challenges. All personnel and deliveries were subject to strict access controls, and close coordination was required to ensure works progressed efficiently without impacting the operation of the facility.
Throughcareful planning and proactive management, McCoy completed all foundations,drainage and reinforced concrete works within the allocated 17-week programme,ensuring the modular installation could proceed as planned.